On many weblogs, quite a few candidates who would like to take the PMP exam right after 31 August 2011 have asked plenty of questions about the actual recent PMP test changes. They wanted to know mainly more in regards to the examination changes. The article under mentions the expected changes in detail.

First of all allow me to explain why PMI has decided to change the PMP examination. As some you may know already, PMI conducts a job delineation study (RDS) for your Project Management Professional (PMP) abilities every five to seven years to ensure that the credential meets today organizations project director needs. Over 3, 000 PMP credential holders from North america, Asia Pacific, Latin America and also the Caribbean regions have got participated in recent RDS study and also the results reveals that how the professional and interpersonal responsibility area needs to be integrated into every one of the work of project supervision. Therefore, PMI decided to improve the PMP evaluation.

What is not really changing? - The education and experience eligibility requirements for that existing PMP assessment remain appropriate and will not be changed. The PMBOK Guide Forth Edition is not changing and exam takers may use that as a reference book.

What is changing? - As per PMI, approximately 30% from the PMP exam content will change. Since the Professional and Social Duty content area may now be tested in every domain, the proportion associated with questions from each domain can change. On the examination, thirteen percentages of questions come from project initiation; twenty four percentages of questions originate from project planning; thirty percentages of questions originate from project execution; twenty five rates of questions result from monitoring and controlling the projects and eight percentages of questions result from project closing.

As we all know final number of questions around the exam is 200[175 questions are scorable questions and 25 questions are unscorable questions (Pre-testing questions)]. Thirty percentages of 175 is 52. 5. Hence roughly fifty-two or 53 questions about the exam will end up being changing. Based on the particular mathematical formula [total number of score-able questions multiplied by % regarding questions on each and every domain multiplied simply by 30 percentage], we can predict a break-up of questions (presented below) that'll be changed to check Professional and Interpersonal Responsibility area in each domains.

* Roughly more effective questions from Project initiation domain will probably be changed.

* Roughly tough luck questions from Project planning domain will be changed

* Roughly fifteen questions from Project execution domain will probably be changed

* Roughly Thirteen questions from Project Overseeing and Control domain will probably be changed

* Roughly four questions from Project Closing domain will probably be changed

Now, let us go through the below two sample questions to analyze the changes.

Before 31 August 2011- Sample PMP exam questions

Question 1: Mr. Joseline Edward is working being a project manager for any construction company. He is operating over budget and also getting pressure in order to cut cost as well as the project sponsor asked to produce a change in the actual scope. He should:

A. Defer the decision in your boss; B. Make sure the consumer understands the effect, and proceed if they do, C. Inform the customer from the scope change procedure D. Assign a specialist to take care of the change

Answer: C

Question 2: Mr. Joseline Edward is working like a project manager to get a construction company. He is preparing cost estimate for any project. He used the actual cost of formerly completed projects to predict the cost of this project. What type of technique he used to estimate project expense.

A. He is utilizing Bottom-Up Estimates, B. He is using Analogous Estimates, C. He is making use of Parametric Estimates and also D. None of the above mentioned

Answer: B

Now, let us see the modified version from the above questions to add professional and interpersonal responsibilities.

After 31 July 2011- Sample PMP examination questions

Question 3: Mr. Joseline Edward is working like a project manager for a construction company. He is working over budget as well as getting pressure to cut cost and also the project sponsor asked to create a change in the actual scope. He has a chance to cut cost through the use of low quality brick that may damage the product from the project after a decade. What should he do? Select the most suitable choice?

A. Yes. The cost/benefits show it is worth to use. B. Yes. The Project Sponsor desires to cut cost regardless of what. C. No. Joseline Edward should not use it. He can turn to cut cost anywhere. D. Joseline Edward should inform to the project shareholders and get their approval and use it.

Answer: C

Question 4: Mr. Joseline Edward is working as a project manager for any construction company. He is preparing cost estimate to get a project. He used the actual cost of formerly completed projects to predict the price of this project and he provided a good estimate just 100% more than the predicted cost from the project. Is he using the right technique to estimate project expense?

A. Yes. He is utilizing Bottom-Up Estimates, B. Yes, He is making use of Analogous Estimates, C. No, He is utilizing Parametric Estimates and D. None of the aforementioned

Answer: D [Reason: even though he could be using the Comparable Estimates, it is not appropriate to use 100% higher than the estimated cost with out a valid reason as well as without getting authorization from stakeholders]

These are all just sample questions. In similar methods, 52 questions on the exam will supply to test the particular exam takers information on Professional as well as Social Responsibilities.

Hence my tip for the exam takers will be, when selecting more appropriate answer out of the four possible options for these types of questions that try to analyze your selection making attitude. Please look in the options from an expert and social duty standpoint. If you think the solution is ethically right for the given situation I might say, that is your best option.